Boiler Installation at University of Tennessee Health Science Center

Nabholz partnered with CS3 to install this 38,000-pound boiler on the busy UT Memphis campus. Other rigging companies in the area declined to perform this particularly challenging equipment installation, which involved inserting the boiler through a small opening in a brick wall while simultaneously lowering it at a 45ยฐ angle to the basement floor seven feet below. It was then rotated 180ยฐ and maneuvered into place, with only one to two inches of clearance in several areas.

 

Project
Related Projects
Have questions or ready to get started?